June 9: Residential street preservation work will resume late-July. The curb replacement program is still in progress through town.
May 28: The contractor is working on the mill and overlay for West Lucy Webb Road between Dean Avenue and Meadowlark Drive.
May 22, 2026 update: Rain has impacted street preservation work several days this week. Work on West Lucy Webb Road will be rescheduled. Here is the tentative schedule for Tuesday, May 26 & Wednesday, May 27, weather permitting:
Tuesday 5/26 Madison Creek Paving
Granite Ct/Dr Paving
Pinnacle Paving
Saddle Peak Paving
Wednesday 5/27: Madison Creek Paving
May 21, 2026 update: ***RAINED OUT 5/22***WEATHER PERMITTING, the contractor plans to mill and overlay West Lucy Webb Road from Dean Avenue to Meadowlark Drive on Tuesday, May 22. Flaggers will direct traffic through the area. The roadway will remain open, however drivers may want to use an alternate route to avoid delays.
RAYMORE, MO (May 7, 2026) - Mill and overlay work starts Monday, May 11, 2026, on North Madison Street and Gore Road.
North Madison will receive mill, patch and overlay work from 155th Street to 163rd Street. Gore Road will receive the same work from North Madison Street to Kurzweil Road.
Streets will remain open during construction. Please use extra caution when driving in construction zones and around workers.
The schedule is dependent on weather and may be delayed in the event of inclement weather.
- Monday, May 11: Milling work on Madison
- Tuesday, May 12: Milling work on Gore
- Wednesday, May 13- Thursday, May 14: Patching work on Madison and Gore
- Friday, May 15: Patching on Gore and paving on Madison; paving on Gore Road