155th Street Reconstruction begins Wednesday, Oct. 25, 2017

Post Date:10/20/2017 12:38 p.m.

 UPDATE: Friday, Nov. 17, 9:15 a.m.: Paving is complete on 155th Street between Kentucky Road and North Madison Street. Crews will be striping the road shortly, but that will not require any closures.

  

RAYMORE, MO - Construction on 155th Street between Kentucky Road and North Madison Street is scheduled to begin Wednesday, Oct. 25, with intermittent road closures between Kentucky Road and North Madison Street. Crews have placed message boards and detour route signs at the affected areas.

Work for this first phase of the 155th Street road improvements includes installing pipe crossings, ditch work, patching and resurfacing the street and is expected to be completed within 30 days, dependent upon weather.

Road closures will begin on Wednesday, Oct. 25, from 7 a.m. to 5 p.m. Crews are not planning any overnight closures.

Anticipated Closure Dates*

Working Days

Closure Location on 155th Street

Oct. 25 & Oct. 26

2

N Madison St. to SW Peterson Road

Oct. 27

1

SW Peterson Road at 155th St.

Oct. 30 & Oct. 31

2

N Foxridge Dr. to Kentucky Road 

Nov. 1 & Nov. 2

2

N Foxridge Dr. to SW Peterson Road

Nov. 3, Nov. 4 & Nov. 5

3

N Foxridge Dr. to N Madison St.

*Schedule updated Oct. 27. All dates are dependent upon weather and are subject to change.

Once pipe crossings are installed and the full depth patch is complete, smaller areas of 155th Street will be closed to traffic throughout the paving process, which is expected to be completed by mid-November.

This project is the first of three phases in the 155th Street Road Improvements and Bridge Reconstruction Project.

In 2015, the City of Kansas City, Mo., which owns half of the bridge and roadway, closed the two-lane bridge just east of Madison along 155th Street. Although Kansas City had no plans to reopen it, the Raymore officials began negotiating with Kansas City to repair the bridge and take it over so Raymore could conduct regular maintenance on the roadway used by many on the northeast side of the City.

Kansas City agreed to pay for half of the $1.4 million project that will expand and repair the bridge and surrounding roadway. Bridge reconstruction is expected to begin before the end of this year and continue through winter.

Visit Raymore.com/CurrentProjects for more information on this and other ongoing projects in Raymore.

 

-------------------

Previous updates:

UPDATE: Nov. 15, 10:57 a.m.: Crews are waiting for pavement to dry out in order to lay the final layer of asphalt. Crews anticipate 155th Street will be closed down in sections tomorrow, Nov. 16,  from North Madison Street to Kentucky Road.  They will start at North Madison Street and work their way west.

UPDATE: Nov. 14, 8:53 a.m.: Rain has delayed the final paving of 155th Street until Nov. 15. 155th Street will be closed down in sections from North Madison Street to Kentucky Road while crews lay the final layer of asphalt.  They will start at North Madison Street and work their way west.

UPDATE: Nov. 13, 9:41 a.m.: 

155th Street will be shut down tomorrow starting at 7 a.m. between North Madison Street and Kentucky Road so crews can put on the final layer of asphalt.
Road work will start at Madison and crews will work their way west, shutting 155th Street down in sections to pave: North Madison Street to SW Peterson Road first; Southwest Peterson Road to North Foxridge Drive; and finally North Foxridge Drive to Kentucky Road.

 UPDATE: Nov. 6, 11:38 a.m.: 155th Street from N Foxridge Drive to Kentucky Road will be closed on Tuesday, Nov. 7, from 7 a.m. to 5 p.m. 155th Street will be open the rest of the week and crews plan to lay asphalt the week of November 13.

UPDATE: Friday, Nov. 3, 5:20 p.m.: On Saturday, Nov. 5, crews will shut down sections of 155th Street for paving and leveling. At 7 a.m., 155th Street will be shut down from N Madison Street to SW Peterson Road, and crews will work their way west throughout the day. Only one section will be closed at a time. Detour signage will be posted.

UPDATE: Friday, Nov. 3, 10:01 a.m.: Crews will be paving 155th Street between Kentucky Road and N Madison Street on Saturday, Nov. 4. Sections of 155th Street will be closed during paving, with only one section closed at a time. Detour signage will be posted.

UPDATE:  Thursday, Nov. 2, 4:47 p.m.: 155th Street is now open. On Friday, Nov. 3, 155th Street will be closed from N Foxridge Drive to Kentucky Road during the first half of the day. When that stretch reopens in early afternoon, N Foxridge Drive to SW Peterson Road will be closed for full depth patch work. 

UPDATE: Thursday, Nov. 2, 10:49 a.m.: N Foxridge Drive to SW Peterson Road is now open. N Foxridge Drive to Kentucky Road will be shut down today until 5 p.m.

UPDATE: Wednesday, Nov. 1, 2:50 p.m.: 155th Street has opened up for the day. It will be closed again tomorrow, Nov. 2, between N Foxridge Drive and SW Peterson Road, between 7 a.m. and 5 p.m. There will also be periods of one-way traffic on 155th Street between Kentucky Road and N Foxridge Drive on Nov. 2. Flagmen will be directing traffic.

UPDATE: Tuesday, Oct. 31, 3:16 p.m.: 155th Street construction continues on schedule. 155th Street will be closed between N Foxridge Drive and SW Peterson Road Nov. 1 and Nov. 2. 

UPDATE: Tuesday, Oct. 31, 8:42 a.m.: Construction is on schedule. 155th Street will be closed today from N Foxridge Drive to Kentucky Road.  

UPDATE: Friday, Oct. 27, 10:05 a.m.: Construction is on schedule, though the closure schedule has changed slightly. On Monday, Oct. 30 and Tuesday, Oct. 31, 155th Street will be closed between N Foxridge Drive and Kentucky Road. On Wednesday, Nov. 1 and Thursday, Nov. 2, 155th Street will be closed between N Foxridge Drive and SW Peterson Road. All closures are scheduled for 7 a.m. to 5 p.m. each day. Detour signs and message boards are posted at the affected areas.

UPDATE: Thursday, Oct. 26, 7:21 p.m.: Construction is on schedule. 155th Street will be open Friday, Oct. 27. SW Peterson Road near 155th Street will be closed on Friday, Oct. 27, from 7 a.m. to 5 p.m. 

UPDATE: Wednesday, Oct. 25, 3:53 p.m.: Construction is on schedule. 155th Street between Madison and Peterson will be closed again tomorrow, Oct. 26, and will reopen tomorrow evening. On Friday, Oct. 27, SW Peterson Road will be closed at 155th Street. 

 

 